Sur IPP · HRSG Thermal Upgrade

Sur Power Plant
HRSG Insulation Improvement

1,022 uninsulated components · 460°C HP zone · Silica/Vermiculite + Rockwool core

Heat Rate improvement ≥ 10–30 kJ/kWh · protects PPA guarantee · payback 0.6 yr

April 2026 · Ref INZ-2026-SUR-001 · UK Patent GB2508992.1

Executive Summary

Project at a Glance

Modular insulation upgrade for 1,022 thermal components at the Sur IPP HRSG area. Based on 8,400 operating hours per year and a net plant heat rate of 6,165 kJ/kWh (LHV).

Annual Fuel Savings
$812,287
54,152 MWh thermal · 18,050 MWhₑ equivalent
Payback Period
~7
months · 3-yr ROI 454%
CO₂ Reduction
9,910
tonnes per year avoided
Project Investment
$449,000
Stage 1: $350,000 (80%)
Heat Rate Improvement
≥ 10–30 kJ/kWh (0.15–0.45%)
Protects the PPA Heat Rate guarantee (OPWP tolling contract). Same HR envelope as a mid-tier condenser upgrade — at < 10% of the cost. Subject to verification against plant 2025 net-export & fuel data.

Exposed HP Surfaces · Continuous Heat Loss

Thermal Survey at Sur IPP HRSG Area

On-site assessment (1–2 June 2025) identified 1,022 uninsulated thermal components: 150 HP support flanges and 150 corrugated expansion joints operating at +460 °C, plus 722 additional elements at +90 to +450 °C across the IP, LP and feedwater lines.

Ambient conditions on site: 27.7 °C, 3.1 m/s wind. Calculation per ISO 12241, VDI 2055 and ASHRAE Fundamentals, aligned with IPCC 2006 Vol. 2 and GHG Protocol for project-level accounting.

  • Continuous convective and radiative heat losses: 54,152 MWh/yr
  • Burn-risk to operators · ambient temperature rise in pipe galleries
  • Insulation "white spots" on valve bonnets, flanges, pumps, steam traps
  • Cladding boxes with sagging insulation >+100 °C on external skin
  • ~9,910 tonnes/yr of avoidable CO₂ emissions (natural gas, 0.183 kg/kWh)
FLIR · HP Support Flange 460°C
FLIR · Corrugated Expansion Joint
FLIR · Valve bonnet hotspot
Scope of Work

1,022 Components · HRSG Area

Priority zone: 300 HP elements at +460 °C (delivering 71% of the total savings). Balance: valves, bonnets, steam traps, flexible joints, flanges and feedwater-pump interfaces across IP / LP / HP lines.

Explore a Typical 460 °C HP Section · Before & After

Drag the slider to compare the exposed support flange and corrugated expansion joint with the Inzonex modular upgrade. Click the orange markers for per-element heat loss, fuel savings and CO₂ avoided. Toggle Thermal Vision to see the 460 °C surface signature.

Construction Detail

How the Clamshell Wraps the 460 °C Element

Front-view schematic of the corrugated expansion joint under the HP support flange — uninsulated baseline vs. Inzonex two-half clamshell with Paroc Lamella Mat 100 mm core.

Uninsulated baseline · front view
Baseline · uninsulated — bare fabric corrugation, hot metal clamp bands exposed, full radiative losses at +460 °C
Inzonex clamshell · front view · Lamella 100 mm
Inzonex clamshell — two half-shells close around the bellows, vertical snap-fit seam (orange), outer surface ≤ 55 °C

Layer build-up (hot → cold)

Equipment Breakdown

Component-by-Component Savings

Top 16 line items of the ISO 12241 heat-loss register. Two HP elements at +460 °C carry 71% of the total annual value.

Zone Component Qty Temp MWh / yr Savings (USD)
HP · 460°C Support Flange (+460°C) 150 460°C 18,326 $274,887
HP · 460°C Corrugated Expansion Joint under Flange 150 460°C 19,989 $299,831
HP Safety Valve (+450°C) 20 450°C 3,982 $59,728
HP Gate Valve (+450°C) 5 450°C 1,288 $19,327
HP Flexible Joints — HP Lines Type 1 (+420°C) 30 420°C 891 $13,369
HP Flexible Joints — HP Lines Type 2 (+420°C) 25 420°C 783 $11,747
IP Disc-type Steam Trap (+276°C) 60 276°C 380 $5,702
IP Flange (+230°C) 10 230°C 68 $1,015
IP Valves (+190-205°C) · 9 lines 160 205°C 964 $14,473
IP Safety Valve (+190°C) 10 190°C 206 $3,094
LP Corrugated Expansion Joint (+180°C) 165 180°C 4,466 $66,994
LP Corr. Exp. Joint — smaller (+180°C) 60 180°C 1,113 $16,694
LP Flexible Joint (+200°C) 100 200°C 1,455 $21,820
LP Flexible Joint (+120°C) 25 120°C 158 $2,371
Feedwater Pump (+120°C) 6 120°C 134 $2,015
Flanges/Valves · misc Flanges & valves (+90-155°C) 66 155°C 133 $1,998
Total (all 1,022 components incl. balance of plant) 1,022 54,152 $812,287

What 54,152 MWh Recovered Heat Means for the Plant

HRSG pipe losses are steam-side — they subtract directly from enthalpy available to the steam turbine. Following the same methodology used on F3 (2025 calendar-year reference, net plant heat rate 6,165 kJ/kWh LHV), recovered steam heat converts to electrical output via the ST at a conservative ratio of ≥ 1:3 (thermal:electrical, Rankine).

Current Thermal Loss
56,179
MWh (thermal) / year · baseline uninsulated
Recoverable Savings
54,152
MWh (thermal) / year · residual 2,027 MWh with Inzonex
Electrical Benefit
≥ 18,050
MWh (electrical) / year · via ST · ratio ≥ 1:3
Heat Rate Improvement
10–30
kJ/kWh · 0.15-0.45% · subject to 2025 net-export verification
Why Heat Rate matters at Sur

A 10–30 kJ/kWh gain protects the PPA guarantee and shifts dispatch economics

PPA Heat Rate guarantee. Sur IPP operates under a long-term tolling PPA with OPWP. Heat Rate is a contracted performance guarantee — drift above the baseline exposes the plant to capacity-charge deductions and fuel-variance penalties. Every kJ/kWh of headroom is a direct hedge against those deductions.

Merit-order dispatch. In the Oman grid, OETC ranks IPPs by short-run marginal cost. A lower HR = lower SRMC = higher dispatch rank = more operating hours & higher capacity-payment realization.

Benchmark context. In the CCGT industry, a 10 kJ/kWh improvement is a notable, press-release-worthy win; 20 kJ/kWh is a board-level KPI line item; 30+ kJ/kWh historically justifies multi-million-dollar upgrade campaigns (condenser overhaul, inlet cooling, gas-path upgrade).

Cost parity. Inzonex delivers the same HR improvement envelope as a condenser-cleaning programme or a mid-tier HRSG performance upgrade — at < 10% of the capital cost and with 0.6-year payback vs 3-8 years for the alternatives.

CCGT HR-Improvement Measure ΔHR (kJ/kWh) Typical Capex Payback
Condenser cleaning / tube replacement10–20$500K–$2M1–3 yr
HRSG performance upgrade (OEM)10–20$5M–$15M4–8 yr
Inlet air cooling (fogging / chiller)40–80$8M–$20M3–6 yr
Advanced gas-path upgrade30–60$30M–$60M5–10 yr
Inzonex HRSG insulation (this proposal) 10–30 $449,000 0.6 yr

Benchmark ranges from public CCGT performance-upgrade case studies (GE, Siemens, Mitsubishi Power, EPRI). Inzonex range subject to verification against Sur 2025 monthly net-export and fuel-consumption data.

The Solution

Inzonex Modular Insulation

Clamshell Construction · Tool-free Access

Inzonex modular insulation for flanges and expansion joints comes as two symmetric half-shells that close around the hot element like a clamshell. Snap-fit fasteners along the vertical seams allow installation and removal in seconds — without tools, without disassembly, without process shutdown.

For the 460 °C HP zone, panels use a silica-fabric hot side with vermiculite coating and a rockwool core. External skin is silicone-coated fabric, fully waterproof and chemically inert. AISI 316 stainless steel snaps and retainers.

Snap-fit Clamshell

Two halves close around the element. Tool-free assembly. 6× faster than wire-tied blankets.

Replaceable Core

Outer shell stays intact · insulation core replaced when needed · lifecycle ~15 years.

🛡

Patent Protected

UK Patent GB2508992.1 · modular segmented architecture with snap-fastening system.

460 °C → ≤ 55 °C

Surface ≤55 °C per our FLIR verification. Operator burn-risk to zero.

Materials & Compliance

  • Outer shell: Silicone-coated fabric · waterproof · chemically resistant · easy to clean
  • Hot-side lining: Silica fabric with vermiculite coating · thermal barrier up to +1,100 °C
  • Insulation core: High-performance rockwool · continuous service to +650 °C · non-combustible
  • Fasteners: AISI 316 stainless snap buttons · Samarium-Cobalt magnets for rapid removal
  • Stitching: Meta-aramid thread · ceramic option to +1,000 °C
  • Certifications: EN 13501-1 Class A1 · REACH / RoHS · ASTM E84

Verification & Warranty

  • Pre-install: FLIR thermography & dimensional survey (on record)
  • Post-install: Thermographic verification · surface ≤60 °C · ESG report
  • Standard warranty: 36 months on shell & fastening system
  • Annual service package (optional): ~10-12% of project value · covers 10% replacement, updated thermography, report refresh

Three-Stage Deployment

Stage 1

Installation

Priority 300 HP elements at +460 °C plus high-temperature valves. Covered without shutdown. ~80% of project value.

8–12 weeks
Stage 2

Full Site Assessment

Thermal measurements of all remaining uninsulated / poorly insulated surfaces during annual shutdown (ST & turbine zones included).

1 week
Phase 3

Full Site Rollout

Complete Inzonex installation across the facility. No critical component left exposed. ESG reporting package & post-install FLIR verification.

8–12 weeks
Investment

Transparent Pricing

Inzonex Modular Insulation — Complete Project
1,022 components · HRSG area · ISO 12241 register
Payback ~7 months · 3-yr ROI 454%
✓ Engineering & per-drawing design — included
✓ Production & quality control — included
✓ Delivery to Sur IPP site — included
✓ On-site installation supervision — included
✓ Post-install FLIR thermal verification report — included
✓ 36-month warranty on shell & fastening system — included
Stage 1 — Priority HP elements (460 °C)
300 units · 80% of project value
$350,000
Total Project Cost (all-inclusive)
VAT & duties not included
$449,000

Ready to Recover 54,152 MWh of Heat?

Start saving $812,287 annually · payback in ~7 months · avoid 9,910 t CO₂ per year.

Approve Proposal →